Infrastructure Case Study
Laverton Bridge - Deck Replacement
Client Gloucestershire Warwickshire Steam Railway
Location Laverton, Worcestershire
Value £225k
Scope
Adroit Construction were responsible installing a new deck to an existing railway bridge structure.
The project involved the following:
- Set up Road Closure & Diversion Route
- Reduce brickwork abutment level
- Install new precast concrete Cill units, Deck beams and parapets
- Drill & dowel beams & cills to existing abutment
- Insitu concrete to deck stitch
- Supply and install new steelwork lattice handrail
- Deck Waterproofing
- Re-build brickwork pilasters, removed to enable original deck to be removed
- Brickwork re-pointing
- Replace existing fencing
Programme
Work commenced mid October 2009 and was completed within the Clients programme of 10 weeks

|