Infrastructure Case Study

 

Laverton Bridge - Deck Replacement

Client Gloucestershire Warwickshire Steam Railway
Location Laverton, Worcestershire
Value £225k


Scope

Adroit Construction were responsible installing a new deck to an existing railway bridge structure.

The project involved the following:

  • Set up Road Closure & Diversion Route
  • Reduce brickwork abutment level
  • Install new precast concrete Cill units, Deck beams and parapets
  • Drill & dowel beams & cills to existing abutment
  • Insitu concrete to deck stitch
  • Supply and install new steelwork lattice handrail
  • Deck Waterproofing
  • Re-build brickwork pilasters, removed to enable original deck to be removed
  • Brickwork re-pointing
  • Replace existing fencing

Programme

Work commenced mid October 2009 and was completed within the Clients programme of 10 weeks