Water - Case Study
Anglian Water Flow
Client
Laing O'Rourke for Anglian Water
Location
100 Sites in Anglian Water area
Value
£650,000
Scope
This batch of contracts involved the supply and installation of flow management solutions on over 100 sewage treatment works within the Anglian Water region.
Adroit Construction Services completed the UWWTD flow measurement scheme under a contract for Laing O'Rourke who were the Principle Contractor to Anglian Water.
This project involved constructing or modifying the flow measurement structures on the 100 sites. The new installations were designed to facilitate such flow measurement solutions as weirs or flumes using state of the art instrumentation to calculate the flow rate.
The majority of installations were designed as open channel flow measurement solutions although in addition Adroit Construction Services constructed Magflow chambers into which Laing O'Rourke installed a closed flow measurement solution.
Back to previous page
|